Attention A T users. To access the menus on this page please perform the following steps. 1. Please switch auto forms mode to off. 2. Hit enter to expand a main menu option (Health, Benefits, etc). 3. To enter and activate the submenu links, hit the down arrow. You will now be able to tab or arrow up or down through the submenu options to access/activate the submenu links.

VA Palo Alto Health Care System

 

Construction in Monterey

Major General William H. Gourley VA-DOD Outpatient Clinic

  • Health Care Center Lease project will include:
    - Developer financed project built on acquired land parcel;
    - Construction of 150,000 square feet for VA and DoD;
    - VA leases back building for extended period of time.
  • Fall 2010-Fall 2012 – VAPAHCS worked with architecture firm, Cannon Design, and VA Real Property to develop design and solicitation documents.
  • Summer 2013 - Construction award
    Press release: Contract awarded to build VA/DOD clinic at former Fort Ord
  • Nov. 11, 2013 - Ground Breaking Ceremony View photos
  • Construction start: Summer 2014
  • Anticipated facility opening: 2016